Tracking cost against budget on projects

Four numbers per cost line track cost against budget: budget, committed, invoiced and forecast final cost. Committed cost, agreed but not yet billed, is what invoice-only tracking misses, and it warns you earlier.

An aerial view of workers in helmets and hi-vis fixing a steel reinforcement cage on a grey concrete floor, with debris and pipes around them.
Cost against budget needs to be visible while the work is still under way.

Budget is the approved cost of the line, before VAT. Committed is what you have signed or ordered, billed or not. Invoiced is what suppliers and subcontractors have billed so far. Forecast final cost is committed, plus your estimate of what is still to buy, plus any risk allowance you still hold.

Why do invoices show an overspend too late?

Because the invoice is the last event in the chain. The price was fixed when you placed the order or signed the subcontract, often weeks or months before the bill arrives.

A material you have ordered is a fixed number. One you have not ordered is an estimate that ages every week. A tracker that cannot tell the two apart gives false comfort.

Where does each of the four numbers come from?

Each has one source document and one moment when it changes. If you cannot name both for a number, nobody owns it.

The four numbers, per cost line
NumberWhat it isComes fromChanges when
BudgetApproved cost of the line before VATEstimate or appraisalA change is approved, with a named approver
CommittedSigned or ordered, billed or notSubcontracts, purchase orders, agreed variationsYou place an order or agree a variation
InvoicedBilled by the supplier so farSupplier and subcontractor invoicesAn invoice is entered
Forecast final costCommitted, plus still to buy, plus risk allowance heldYour monthly review of each linePrices, scope or risk change

Variance is forecast final cost minus budget. A positive number is an overspend. The gap between committed and invoiced is what you still owe on work already priced.

  • A change the client has asked for but not yet agreed goes in the forecast as an anticipated item, marked not instructed. It stays out of committed until it is agreed.
  • A price given by phone goes in still to buy, with the date, until it is on an order.
  • A supplier credit note reduces invoiced cost on that line and is entered with the same date discipline as an invoice.
  • Work you will do with your own labour needs a line too, costed at an hourly rate you set once and review each quarter.

The RICS guidance note on cost reporting, first edition March 2015, builds a report the same way: costs incurred, known costs, forecast costs and risk allowances. It also says to mark anticipated instructions as not yet issued, and to update monthly. It is a guidance note for surveyors, not a rule for you. RICS has since reissued a cost prediction standard (June 2024), which we have not reviewed, and we could not confirm whether the 2015 note has been replaced, so check the current RICS standards.

What does a cost report look like for one job?

Five lines and one total. All figures are illustrative, before VAT, and invented for the example.

Illustrative cost report for one refurbishment (pounds, before VAT)
Cost lineBudgetCommittedInvoicedForecast final
Groundworks18,00018,00018,00018,000
Structural steel24,00027,5009,00027,500
Electrics12,00013,800013,800
Finishes30,0008,000032,500
Risk allowance6,000006,000
Total90,00067,30027,00097,800

Steel was ordered after a price rise. Electrics include an agreed £1,800 variation. Finishes forecast is £8,000 committed plus £24,500 still to buy.

The £1,800 only appears here because someone recorded the change when it was agreed. How to capture that on site is covered in quote to site update for construction firms.

What do UK rules add to the cost record?

Three things: VAT is kept out of the figures, subcontractor payments carry CIS deductions, and reports follow a monthly rhythm. This describes the rules and is not tax or legal advice, so confirm treatment with your accountant.

  • VAT. For invoices under the domestic reverse charge, the HMRC technical guide says the supplier must not include the VAT in the amount charged. Record the cost before VAT in every case, and flag lines where the reverse charge applies so the invoice is entered correctly.
  • CIS. HMRC sets deductions of 20 per cent for registered subcontractors, 30 per cent for unregistered and 0 per cent for gross payment status, applied after removing VAT, materials the subcontractor paid for directly and some other costs. A payment and deduction statement is due within 14 days of the end of each tax month. In our reading, which HMRC does not state and your accountant should confirm, the deduction changes the cash you pay the subcontractor, not what the job costs, so keep it off the cost line.
  • Returns. GOV.UK says a contractor must file monthly CIS returns and keep full records. A cost record that holds the labour and materials split per invoice makes both jobs easier.
  • Reporting rhythm. The RICS note says update monthly and show the approved budget the variance is stated against. A change to budget needs a named approver and a date, or the variance means nothing.

If you intend to pay a subcontractor less than they claimed, notice timing applies. That, and the retention changes now before Parliament, are set out in the payment rules section of our site update article.

What would we build for a property or construction firm?

A proposal to test with you, not delivered work, for firms in property and construction running several jobs at once.

  • One cost record per job with a line per cost code, holding budget, committed, invoiced, forecast and the date each was last reviewed.
  • Purchase orders and subcontract orders raised in the system, so committed cost is entered at the moment of ordering rather than reconstructed later.
  • Supplier invoices matched to the order. Where a model reads the invoice, it proposes the line and amount and a person confirms, because a mismatch is the signal you want to see.
  • A monthly report across all jobs, in the five-number style of dashboards that get used, built from the same records and not rebuilt in a sheet.

If a construction accounting or job costing package already handles purchase orders and subcontract commitments, use it and add what it lacks. Custom work is for the case where your cost codes, approval limits or reporting to lenders and clients do not fit.

What can you try this week without us?

  1. 1

    Pick one live job

    Choose the one with the most spend still to come.

  2. 2

    Add the committed column

    List every signed subcontract and placed order against its cost line, billed or not.

  3. 3

    Price what is left

    For each line, write what is still to buy and the date of the price you used. Mark anything older than a month.

  4. 4

    Calculate the forecast

    Committed plus still to buy plus risk allowance held, per line, then the total against budget.

  5. 5

    Repeat monthly

    Keep each month’s copy so you can see which lines drifted, not only the total.

Questions people ask

It is the cost you have agreed to but not yet been billed for: a signed subcontract, a purchase order or an agreed variation. It matters because the price is fixed at that point. Tracking only invoices means you learn about an overrun when the bill arrives, which can be weeks or months after the decision.

Monthly at least, and whenever a large order or variation is agreed. The RICS cost reporting note recommends monthly updates. On a fast job with volatile materials, a short weekly look at the lines still to buy catches price moves before they are ordered. Record the date of each update so a stale forecast is visible.

The RICS cost reporting note advises against a general contingency in reports and prefers named risk allowances that reduce as the related costs emerge. That is guidance for cost reporting, not a rule for your pricing. Whatever you hold, show it as its own line so it is not spent unseen.

A spreadsheet works for a few jobs when one person enters every order and invoice. It fails when orders are placed by several people, when invoices are keyed late, or when you need one view across jobs. Look at a package made for construction first, and consider custom only for gaps it leaves.

Further reading

Have a problem this does not solve?

Book a discovery call. Tell us what is slowing the business down, and we will say what we would build and whether it is worth doing.

Book a call

Start here

Tell us what takes your team time.

Leave a few lines and we will reply by email.

Or email [email protected]

Company size

Used to reply to you. See our privacy notice.