90 day systems plan after an acquisition
Run the first 90 days of systems work after an acquisition in three blocks: secure and see by day 10, agree definitions and customer data by day 45, connect and decide by day 90, with a test at each gate.

It is day 40. The two sales teams still use different systems, a supplier has sent a renewal notice for a tool you were going to drop, and a director has asked for one revenue figure by Friday. A plan with dates and gates is what stops each of those becoming an emergency. This is the last part of the series: it puts the earlier parts in order, adds the dates, and says what to leave alone until after day 90.
What belongs in a 90 day systems plan, and what waits?
Keep the business running, see what you now own, agree what the numbers mean and make cheap connections. Leave replacing core systems until after day 90, once you know what you hold.
BCG's 2024 article on technology in post-merger integration describes the first 100 days as keeping the business running, connecting the two companies' networks and tools, and unifying cybersecurity, with platform merging and data harmonisation later. It suits large companies and its governance is too heavy for a firm of 15 to 200 people, but the sequence holds.
The Umbrex integration playbook cautions that 30, 60 and 100 day horizons should not become arbitrary deadlines. Use the dates below as review points, and move one only for a reason you write down.
What should happen in each block?
The table is the plan. Each row has a goal, the work and a gate you can check. Day 1 is completion.
| Days | Goal | Do | Gate: must be true to move on |
|---|---|---|---|
| 1 to 10 | Secure and see | Access register started and email, domain and bank secured. List of every system, with owner, cost and renewal date. Backups confirmed. No new tools bought, no migrations started. | Every system has an owner. Two named administrators on your side for email and finance. Nothing is changing that you did not choose. |
| 11 to 45 | Agree | Definition sheet for six to eight measures. Customer lists matched. A first keep, connect or retire view of each system. Contract notice dates calendared. | Both finance leads have signed the definitions. The duplicate rate in the merged customer list is known. Every renewal inside 120 days has a decision date. |
| 46 to 90 | Connect and decide | Run the first combined month end from the mapping table. Make the cheap connections. Retire duplicate low-risk tools. Decide the identity and email platform. Draft the next 12 months. | One combined close has passed the four checks. The retire list is done or dated. Directors have approved the next-year plan. |
The gates are our suggestion, not a published standard. A gate that is missed is information: say why, set a new date, and do not quietly skip it.
Everything in the "do" column has a full article behind it. The first week is in first week after buying a business. Merging customer lists is in two CRMs, one customer list.
What matters most in days 1 to 10?
Control and visibility. You are not improving anything yet. You are finding out who can log in, what exists and what is about to renew.
- Start the access register and secure email administration, the domain and the bank first. The order and the method are in system access after a deal completes.
- Build one list of systems with the owner, what it holds, the monthly cost, the renewal date and the notice period. A spreadsheet is fine.
- Confirm backups exist for anything holding customer, finance or job data, and that someone has seen a restore work.
- Freeze purchases. A new tool bought in week two becomes one more thing to retire in month three.
The gate is control, not completeness. If you cannot yet say what every system does, that is fine. If you cannot say who administers email, stop and fix that first.
What do you agree in days 11 to 45, and with whom?
You agree three things: what the key measures mean, who your customers are, and which systems stay. Each needs two people, one from each business, to sign it off. A decision made by one side only is the one that gets reopened in month four.
- Measures: the definition sheet in one set of numbers across two businesses, signed by both finance leads.
- Customers: match the two lists, record the duplicate rate, and decide which system holds the master record. Check what the ICO says about data sharing after an acquisition: identify the original purposes of the data and document what you do with it. The ICO says that page is under review.
- Systems: sort every system into keep, connect or retire using the test in keep, connect or retire. Draft only, until the contracts are read.
Which decisions does a contract date force on you?
Any tool you plan to drop that renews inside the plan. Take the renewal date, subtract the notice period, and then subtract a margin. The result is your decision date, and it can land in the middle of the "agree" block.
| Tool | Renews on day | Notice needed | Last day to give notice | Decide by (5 day margin) |
|---|---|---|---|---|
| Duplicate reporting tool | 100 | 60 days | 100 - 60 = day 40 | Day 35 |
| Second CRM, annual | 150 | 90 days | 150 - 90 = day 60 | Day 55 |
| Survey tool, rolling monthly | Any | 30 days | Any day | No date forced |
The margin is our suggestion. Check the real notice wording, since some contracts count from the date of a letter being received and some require a particular method.
The first contract needs its decision on day 35, before most of the customer and finance work is done. That is the point of the table: it shows which decisions you cannot leave. If you miss the date you may pay for another term, which may cost less than a rushed decision. CBIZ, a US advisory firm, also advises checking for change-of-control clauses that could end a service. This is operational guidance and not legal advice, so have contracts that matter read by your adviser.
What do you connect and decide in days 46 to 90?
Run the first combined month end, make the cheap connections, and decide the platform questions that need an answer. Do the cheap things now, and leave the expensive ones to the next-year plan.
- The first combined close uses the mapping table. A vendor article by Nominal suggests the third close after a deal is a better measure of success than the first. If you completed mid-month, you may have two or three closes by day 90.
- Cheap connections first: a shared export, a scheduled import, a common report. The options and where they break are in connecting Outlook, Xero, HubSpot and your own system.
- Identity and email: Microsoft's tenant-to-tenant migration overview, updated June 2026, lists what to plan: how identities map, whether people keep their address, how domains move, and whether licences are enough. It gives no durations, because they depend on mailbox and file volumes. Decide now whether you will merge, and plan the move for later.
- Retire the duplicates that passed the keep, connect or retire test, and have already run past their notice date.
Umbrex notes that a platform decision may need making within the first 60 days. For a small group, that means choosing the direction, such as one email tenant or one CRM, by day 60, and the migration itself after day 90.
How do you tell whether the plan is working?
Hold a 30 minute review each week on one page: the gates, the dated decisions and the open risks. Each item has one owner and one date, and a missed date is discussed, not rolled over.
In the 2026 PwC M&A integration survey of 530 senior executives at companies with $1 billion or more in revenue, 46% said they fully translated value drivers into initiatives with owners, timelines and dependencies before integration. It was 59% for acquirers reporting success and 28% for limited success. The survey is self-reported, shows association not cause, and covers far larger deals than yours. Take it as a reason to write names and dates down.
- Gate 1 check: ask any person to name the administrators of email and finance. They should all give the same two names.
- Gate 2 check: pick ten customers at random and compare the record in both systems with the merged list. The duplicate rate should be falling.
- Gate 3 check: the combined close adds back to each ledger, and the figure the directors saw this month matches the definition sheet.
What should wait until after day 90?
Replacing core systems, renumbering ledgers, rebuilding workflows and adding AI tools. Each is easier once the definitions are agreed and the data is clean, and each is harder when the team is still learning who does what.
- Moving both businesses onto one finance or operations platform. DealRoom, a software vendor, estimates 6 to 18 months for integrating finance and operations systems. That is a vendor estimate, not independent research, but it suggests the work runs well past day 90 even where it starts early.
- Custom builds. Decide what to build once the next-year plan shows which gaps connecting tools cannot close. Build, buy or configure gives the test.
- New AI tools on top of data you have not yet checked. What leaves your building when staff use an AI tool is the place to start before any is approved.
Questions people ask
For the three blocks here, yes: securing access, agreeing definitions and customer data, and running a first combined close are achievable with a small team. Replacing core systems is not, and should not be attempted in the same window. Treat the dates as review points, and move one only when you can write down why.
One named person on the buyer's side, usually the operations lead or finance lead, with a director as sponsor. Each gate and each dated decision has its own owner, one from each business where the work touches both. A plan owned by a committee, or by an outside adviser alone, tends to stall when a decision needs making.
Keep the plan counted from completion, and place the first combined close at the next full month end. You may then run two or three month ends before day 90, which helps, because the third close is a fairer test of the mapping than the first. Check with your accountant how the part-period is reported.
Often for the email and identity migration, and for any custom connection that needs building, and rarely for the definitions, the customer decisions and the owners, which only your people can settle. Ask any provider for a fixed scope with named outputs and a handover, and check what access they will hold afterwards.
Further reading
- BCG: Technology's role in the post-merger process (March 2024)
First 100 days: keep the business running, connect, unify cybersecurity; later platforms and data. For large companies. Free.
- Umbrex: Building the 30-, 60- and 100-day integration plan
Horizons are not arbitrary deadlines; platform decision may be needed within 60 days. It does not name systems or data milestones. Free.
- PwC: 2026 M&A Integration Survey (summarised by the Harvard Law School Forum on Corporate Governance, 21 October 2026)
530 executives at companies with $1 billion or more in revenue, self-reported. The 46, 59 and 28 percent figures match the PwC page and the Harvard summary. Used for the owners and timelines figure only. Free.
- Microsoft Learn: Microsoft 365 tenant-to-tenant migrations
Planning factors: identity, workload dependencies, coexistence, licences. Last updated June 2026, with no durations stated. Free.
- ICO: Due diligence when sharing data following mergers and acquisitions
Original purposes, documenting use, accuracy and retention. The ICO says the page is under review. Free.
- CBIZ: After the close, post-deal technology integration (September 2025)
US advisory firm. Day 1, 90 and 180 phases; check vendor contracts for change-of-control clauses. Its two statistics are secondhand and unused. Free.
- Nominal: post-merger accounting integration
Vendor article. The third close as a better measure than the first. Omits UK specifics. Free.
- DealRoom: Finance integration after M&A
Vendor article. Its estimate of 6 to 18 months for systems integration is the vendor's own, not independent research. Free.
AIforCompanies · https://aiforcompanies.co.uk/insights/90-day-systems-plan-after-an-acquisition
Have a problem this does not solve?
Book a discovery call. Tell us what is slowing the business down, and we will say what we would build and whether it is worth doing.